Santa Monica Beach Restoration Pilot Project – Project Update Report December 2016

This report summarizes activities for the Santa Monica Beach Restoration Pilot Project from the time period December 2015 through the end of November 2016. During this time period, substantial outreach was conducted, the partnership and Memorandum of Understanding (MOU) between The Bay Foundation (TBF) and the City of Santa Monica was finalized, permitting was applied for and finalized, and the installation of the project and restoration activities commenced.